Installation checklist 75
The external line circuit breakers are adequately sized. See AC Output data and grid
requirements on page 114.
The AC distribution board is installed, wired and inspected correctly and according to
local regulations.
All shrouds and covers are in place and secured.
Serial numbers of installed inverters:
Installation checked (DD/MM/YYYY):
Installers’ signatures:
Electrical installation (see Electrical installation on page 57)